Posted on: April 23, 2021

Northside Drainage Improvements Project Construction Underway

Brownsburg placeholder

Work is currently underway and will continue through December 2021, with landscaping to be completed in Spring 2022. The roads listed below will have restrictions or will be closed during  construction.  

This will be a lengthy major project; we appreciate your patience during construction.  

Schedule dates may change due to weather and unknown site conditions discovered during construction.


Contract A Areas:

Jefferson St. - May 5-September 16

Parthenia Ave. - May 5-September 3

Adams St. - May 5-August 30

Grant St. - June 1-November 2


Contract B Areas:

Jefferson St. - July 1-November 15

Vermont St. - September 24-December 2

Copeland. - October 11-November 22

Adams St. - October 25-November 26

Railroad St. - November 18-November 19